Page updated September 17, 2015
Clicking on the images below will take you to more project information | ||
Ashville's Portion of Joint Project | Pickaway County Engineering Project |
Project Schedule
-
July 30th Kokosing will mill butt joints on Ashville Pike/Long Street. COMPLETED
-
July 31st fill and mill locations will be marked. COMPLETED
-
Tuesday, August 4th KMC will make pavement repairs moved from August 3rd because of weahter. COMPLETED
-
Thursday, August 6th Kokosing plans to begin paving with leveling course moved from August 5th because of weather. COMPLETED
-
Once leveling has been completed Kokosing will pave. COMPLETED
-
Berming on Ashville Pike/Long Street. COMPLETED
-
September 17th Griffin Striping will be marking the pavement on Ashville Pike/Long Street.
-
September 21st Raised Pavement Markers (RPM) will occur.
We will attempt to keep this page up to date. Project updates projvided by Lance Boyer, Construction Inspector/Permit Coordinator, Pickaway County Engineer’s Highway Department, Phone: (740) 474-3491 Fax: (740) 477-1784