Four Way Stop
One of our longer and complicated projects is nearing completion. On November 18, 2013 the village had a Pre-Construction meeting with Decker to begin work at the intersection of St. Rte. 752 and Long Street.Since then, the utility companies have worked to bury the utility cables. That process is near completion. The utility work will be completed by June 17th. Decker Construction will be returning to complete the project after July 4th. They will complete the project by September 22, 2016.When the utilities are buried there will be no support for the traffic signal. Therefore, this intersection will temporarily become a four way stop, see below diagram.The new signal will be installed as part of the project with a automated pedestrian cross walk. |
Decker Construction arrived in the village to work on stormwater. They will be in the village for 3 to 4 weeks. Please contact thte office if you have any questions.