Updated November 7, 2016
Updated on November 8, 2016 with photos of project
Updated on May 23, 2016 with revised time-line and intersection as a 4-Way Stop.
his page is created to keep you informed about the intersection improvement at State Route 752 and Long Street. The project has received funding from the Ohio Public Works Commission - $500,000 Grant and $325,108 Loan over 20 years. Below is the application and the attachments that provided the information resulting in approval of the Grant/Loan:
Revised timeline below: Click on image will open pdf of "Timeline", OPWD "Request to Proceed", and revised schedule.
Utility work resumed on May 9, 2016 the below photos reprsent work by South Central Power, click on cover to access pdf file.
Project Work in Photos
|
|
|
Four Way Stop
One of our longer and complicated projects is nearing completion. On November 18, 2013 the village had a Pre-Construction meeting with Decker to begin work at the intersection of St. Rte. 752 and Long Street.Since then, the utility companies have worked to bury the utility cables. That process is near completion. The utility work will be completed by June 17th. Decker Construction will be returning to complete the project after July 4th. They will complete the project by September 22, 2016.When the utilities are buried there will be no support for the traffic signal. Therefore, this intersection will temporarily become a four way stop, see below diagram.The new signal will be installed as part of the project with a automated pedestrian cross walk. |
Decker Construction arrived in the village to work on stormwater. They will be in the village for 3 to 4 weeks. Please contact thte office if you have any questions.
Project Timeline
Click on the image above for a pdf version
Ohio Public Works Commision (OWPC)
Click on the image to the right for the Public Notice for the Project:
Circleville Herald Public Notice on October 17, 2013 Circleville Herald Public Notice on October 24, 2013
Bid Documents for PIC-752/Long Street Improvements OPWC Project CT72N/CT73N below
PIC-752/Long Street Improvements OPWC Bid Book | Addendum #2 | Drawings #1 |
Drawings #2 | Traffic Drawings and Information | Appendix A |
OPWC Information | Prevailing Wage |
Contract for PIC-752/Long St. Improvements OPWC Project CT72N/CT73N below
Contract Decker Construction & Village of Ashville | 12-2013 Resolution Village of Ashville | Request to Proceed |
Notice to Proceed from OPWC | Connnect to Decker Construction | |
Pre-Construction Meeting |
The Stormwater Center Alley Project is not directly part of the above project but was added to improve water drainage in the same area. The ($92,000) Center Alley Project has begun. Click on the following icon to read the letter sent to the residents in the area:
The letter encourage residents and businesses in this area to contact Franklin Christman at 740/983-7164 if they are interested in connecting to this stormwater main. This connection could include gutters, sump pumps, and yard drains.
February 10, 2012 Cox Paving has completed from South Street to Hall Street. Columbia Gas will be doing some line work between Hall Street and State Route 752 during the early part of February 13.
On February 20, 2012 Cox Paving is now north of Hall Street moving toward State Route 752.
The Village of Ashville is working with South Central Power, Frontier Communication, and Time Warner to remove all poles that are located at this intersection. Meetings have been very encouraging.
The 2009 drawing below represents the early concept for revising the intersection of State Route 752 and Long (316) Street. An engineering firm is refining this drawing. When it is available it will replace the one below. By clicking on the image you can download a pdf that is more well-defined.