Page updated September 17, 2015

Clicking on the images below will take you to more project information
      Joint Project Paving             Page 0 Joint Project
Ashville's Portion of Joint Project   Pickaway County Engineering Project

Project Schedule

  • July 30th Kokosing will mill butt joints on Ashville Pike/Long Street. COMPLETED

  • July 31st fill and mill locations will be marked. COMPLETED

  • Tuesday, August 4th KMC will make pavement repairs moved from August 3rd because of weahter. COMPLETED

  • Thursday, August 6th Kokosing plans to begin paving with leveling course moved from August 5th because of weather. COMPLETED

  • Once leveling has been completed Kokosing will pave. COMPLETED

  • Berming on Ashville Pike/Long Street. COMPLETED

  • September 17th Griffin Striping will be marking the pavement on Ashville Pike/Long Street.

  • September 21st  Raised Pavement Markers (RPM) will occur.  

We will attempt to keep this page up to date. Project updates projvided by Lance Boyer, Construction Inspector/Permit Coordinator, Pickaway County Engineer’s Highway Department,            Phone: (740) 474-3491        Fax: (740) 477-1784