December 16, 2021 Update
Disburesement through 12/16/2021
A/P-SYS-036586 WorksWise Portal Information
200143 ODOT/Engineer's Punch List
October 11, adjusted October 15, 19, & 26, 2021Long Street: Newcomer Concrete has completed most curbs & sidewalks. Strawser Paving will be moving to Long Street & completing West Main east of the Norfolk Southern Crossing. The following is the anticipated schedule range, weather & road condition discovery dependent: Eastside of Long Street- October 15-16 Milling first half of existing pavment
- October 18-22 After milling repairs to roadway surface
- Week of October 25th after milling & repairs paving will begin
- Paving on the eastside of Long & the southside of West Main after the Norfolk Track started on October 26th
- Week of October 25th Milling second half of existing pavement
- October 28-29th After milling repairs to roadway surface
- Week of October 30th After milling & repairs paving.
West Main Street: Once all work has been completed, a walk through will occur to gernate a "Punch List."
As this project nears completiion be aware of some road, driveway and alley closures. As we become aware of information this page will be updated. Please call 740-983-6367 if you have questions or have information to report. You can also find out information on the "Project Meeting" tab to the right. Thank You.
October 5, 2021, Update
Long Street: Newcomer Concrete has completed most curbs on the eastside of Long Street. They are working on sidewalks south of Wright Street through the downtown area. As this takes place access to roadways or driveways will be interrupted until concrete work has been completed. Newcomer Concrete has also resumed work on the westside. This is concentrated south of Station and north of Madison Avenue. Please make arrangement for this disruption. We regret this inconvenience, but this infrastructure improvement is important.
West Main Street: Strawser Paving has completed roadway repairs and paving. The next objective will be to complete stripping, landscapting and bring manhole & covers up to grade.
As this project nears completiion be aware of some road, driveway and alley closures. As we become aware of information this page will be updated. Please call 740-983-6367 if you have questions or have information to report. You can also find out information on the "Project Meeting" tab to the right. Thank You.
September 28, 2021, Update
Long Street: Newcomer Concrete has completed most curbs on the eastside of Long Street north of Plum Street. They are now working on sidewalks, road and driveway approaches. They are working on sidewalks south of Plum Street through the downtown area. As this takes place access to roadways or driveways will be interrupted until concrete work has been completed. Newcomer Concrete has also resumed work on the westside. This is concentrated sough of Madison through the downtown area. Please make arrangement for this disruption. We regret this inconvenience, but this infrastructure improvement is important.
West Main Street: Strawser Paving has completed roadway repairs. They plan to work on the final application of pavement on Tuesday, September 28th. Once completed the pavement will be painted with strips. As Strawser Paving and Newcomer Concrete completes their work landscaping should follow. As above, this may result in single lane traffic and some roadway and driveway closures.
As we become aware of information this page will be updated. Please call 740-983-6367 if you have questions or have information to report. Thank You.
September 20, 2021, Update
Long Street: Newcomer Concrete has completed most curbs on the eastside of Long Street. They are now working on sidewalks, road and driveway approaches. As this takes place access to roadways or driveways will be interrupted until concrete work has been completed. Please make arrangement for this disruption. We regret this inconvenience, but this infrastructure improvement is important.
West Main Street: Strawser Paving continues to make roadway repairs. This is done to prepare the roadway for paving. As above, this may result in single lane traffic and some roadway and driveway closures.
As we become aware of information this page will be updated. Please call 740-983-6367 if you have questions or have information to report. Thank You.
September 10, 2021 Update
The State Route 316 Project has resumed. It began with some surveying and status assessment.
Newcomer Concrete out of Norwalk has returned to the village. They began on September 9th placing no parking signs and site preparations. On September 10th they began removing sidewalks on the east side of Long Street. This started at Station Street and they are moving South. They are also working at about 64 Long Street. After this excavation is completed, framing will occur followed by laying of concrete.
ODOT has arranged with Strawser Paving to begin works on West Main Street. The objective of Strawser will be to make concrete repairs on West Main Street on Monday and Tuesday, September 13th and 14th. They plan to complete the partial and full depth asphalt repairs on Thursday and Friday, September 16th and 17th. Their future objective will be pave the surface course asphalt early the week of 9/20. These road repairs would be necessary before paving can take place.
Please come back to this webpage for updates on the progress. Nicholson Construction who is representing the bonding company of the previous contractor has stated their objective is to complete this project this year.
September 3, 2021 ODOT Message
The surety plans to have a surveyor on site September 3 ,2021 to help assess the remaining work. They also plan to have a crew on site Wednesday or Thursday, September 8 or 9, to resume with curb removal on Long Street. ODOT is working with their consultant to get a six-week look ahead. When they have information they will provide an update.
Village Council was updated on the status of the project on August 9 and 16, 2021
ODOT continues to work with obtaining a Contractor and working with AMAAZZ's Bonding Company.
August 3, 2021
Amaazz has been removed from the project. ODOT has no timeline of days for work. The bonding company from Amaazz is now engaged. ODOT will make additional efforts to address the milled surface on Main Street if they anticipate delays."I would try to emphasize that these efforts are being made to complete the project in a timeframe that Amaazz had demonstrated could not have been achieved previously."
Thanks.
Ian Downing, P.E.
Project Engineer
ODOT District 6 Construction
400 E. William Street, Delaware, Ohio 43015
Cell: 740.447.2859
transportation.ohio.gov
Updated July 21, 2021
The State Route 316 Project has reached Long Street for installation of sidewalks, alleys, streets, and driveway approaches. As they reach each area, moving south to north, areas will be closed. Therefore, it will be necessary to find alternate places to park your vehicle or for pedestrians to walk. The eastside sidewalk will be open until the westside sidewalk is completed. That would be followed by the closing of the eastside sidewalk but you will be able to use the new westside sidewalk. During this process that same thing will happen as concrete work is occurring for alleys, streets, and driveways. You will be notified when you can to begin using those roadways or drives. As part of this process please refrain from parking on the street when road work is occurring. Signs will be posted. We appreciate you patience’s during this construction project. Thanks.